Procurement of International Designers requirements, as well as the difficult transport logistics, determined the completion of the project.
Zimbali Lodge
Detail operating criteria
completed early in the construction process facilitated
the briefing of the operations
team and ensured that the
planned philosophy was
implemented.
CASINOS:
Meropa
Bird, reptile and butterfly park operational requirements coordination and opening within an extremely fast-track programme, provided an extremely rewarding challenge.
Sugarmill
Meeting stringent requirements
for empowerment, involved a
completely new emphasis on
project negotiation and control.
COUNTRY CLUBS AND HEALTH SPAS:
Zimbali CC
Research on the top country
clubs in South Africa ensured
that design, finishes and
services compare with the best.
Royal Swazi
Understanding the marketing
aspects of the health and
beauty industry, helped to focus
the operating and design
criteria.
COMMERCIAL PROPERTIES:
Old Mutual 1066
Design and implementation of
hi-tech “table” formwork
system allowed structure to be
completed ahead of programme.
REFURBISHMENTS:
Gaborone
Hotel & Conference facilities
By allowing and properly utilising
pre-contract lead time, project
implementation proceeded
extremely smoothly, despite this
being over the builders break.
Saint Geran
Hotel: Mauritius
Being responsible for
procurement of all materials,
sourced fromHong Kong to Los
Angeles, proved to be extremely
challenging and required
accurate control and proactive
management.